Contains Nonbinding Recommendations
13
the reasons for the transfer and the risk posed by the study. In the case of a natural
disaster, although the transfer may initially be thought to only be required for a short
period of time, additional time may ultimately be needed before the original IRB is able
to resume its oversight responsibilities. The original and receiving IRBs would need to
ensure that study oversight does not lapse; adverse events are reported to the appropriate
IRB, etc. during this interim period.