Reference Specifications for Civil Engineering Work 2001


Placing Base and Sub Base



Yüklə 138,39 Kb.
səhifə8/22
tarix26.12.2016
ölçüsü138,39 Kb.
#3344
1   ...   4   5   6   7   8   9   10   11   ...   22

3.2Placing Base and Sub Base


General

Material separation: Place materials of different grading or from different sources in separate layers or separate sections of the work.

Spreading: Spread material in uniform layers. Do not segregate the material.

Layer thickness: 100-150 mm (after compaction) to suit the construction process. Use equal layers in multi layer courses.

Moisture content of underlying layers: Adjust the surface moisture content of underlying layers to prevent new material losing moisture.

Joints

Plan the spreading and delivery to minimise the number of joints. Offset joints in successive layers by at least 300 mm.



Existing road surface as subgrade

Carry out minor reshaping to improve vertical alignment as directed. Do not otherwise lower or excavate the existing roadway. After final shaping of the metal box, scarify the existing pavement forming the subgrade before placement of the pavement material.



Yüklə 138,39 Kb.

Dostları ilə paylaş:
1   ...   4   5   6   7   8   9   10   11   ...   22




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©www.azkurs.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin