0027/nd guidelines for Marine Lifting and Lowering Operations



Yüklə 1,31 Mb.
Pdf görüntüsü
səhifə3/97
tarix01.07.2022
ölçüsü1,31 Mb.
#62589
1   2   3   4   5   6   7   8   9   ...   97
0027-nd rev 11.2 8-jul-16 guidelines for marine lifting and lowering operations

GUIDELINES
 
FOR
 
MARINE
 
LIFTING
 
&
 
LOWERING
 
OPERATIONS 
0027/ND Rev 11 
 
Page 3 of 84 
CONTENTS 
SECTION 
PAGE NO. 
1 
SUMMARY 
6 
2 
INTRODUCTION 
7 
3 
DEFINITIONS & ABBREVIATIONS 
12 
4 
THE APPROVAL PROCESS 
18 
4.1 
GL Noble Denton approval 
18 
4.2 
Scope of work leading to an approval 
18 
4.3 
Approval of moorings 
19 
4.4 
Limitation of approval 
19 
4.5 
Surveys 
20 
5 
LOAD AND SAFETY FACTORS 
21 
5.1 
Introduction 
21 
5.2 
Weight contingency & centre of gravity factors 
23 
5.3 
Module tilt for single crane lifts 
23 
5.4 
2-Hook lift factors 
23 
5.5 
Dynamic amplification factors 
24 
5.6 
Skew load factor (SKL) 
25 
5.7 
Additional factors 
27 
5.8 
2-Part sling factor 
27 
5.9 
Lift stability 
27 
6 
DERIVATION OF HOOK, LIFT POINT, AND RIGGING LOADS 
28 
6.1 
Introduction 
28 
6.2 
Hook loads 
28 
6.3 
Lift point loads 
29 
6.4 
Sling loads 
29 
7 
SLING AND GROMMET DESIGN 
31 
7.1 
Introduction 
31 
7.2 
Sling or grommet design 
31 
7.3 
Sling or grommet nominal safety factors for design 
31 
7.4 
Load factor 

f
 
32 
7.5 
Consequence factor 

c
 
32 
7.6 
Sling or grommet reduction factor 

r
 
32 
7.7 
Termination factor 

s
 
32 
7.8 
Bending factor 

b
 
33 
7.9 
Wear and application factor 

w
 
34 
7.10 
Material factor 

m
 
34 
7.11 
Twist factor 

tw
 
34 
8 
SHACKLE DESIGN 
35 
8.1 
Introduction 
35 
8.2 
Design considerations 
35 
9 
OTHER LIFTING EQUIPMENT DESIGN 
36 
9.1 
Introduction 
36 
9.2 
Lifting tools 
36 
9.3 
Spreader bars and spreader frames 
36 
9.4 
Other lifting equipment 
36 
9.5 
Fibre rope reployment systems 
36 
10 
THE CRANE AND INSTALLATION VESSEL 
38 
10.1 
Introduction 
38 
10.2 
Cranes 
38 
10.3 
Hook load 
38 
10.4 
Heave compensation 
38 


GUIDELINES
 
FOR
 
MARINE
 
LIFTING
 
&
 
LOWERING
 
OPERATIONS 
0027/ND Rev 11 
 
Page 4 of 84 
10.5 
Installation vessel 
39 
10.6 
DP systems (if applicable) 
39 
10.7 
Mooring systems (if applicable) 
39 
11 
STRUCTURAL CALCULATIONS 
40 
11.1 
Codes and specifications 
40 
11.2 
Load cases and structural modelling 
40 
11.3 
Structure 
40 
11.4 
Consequence factors 
40 
11.5 
Lift points 
40 
11.6 
Spreader bars, frames & other structural items of lifting equipment 
41 
11.7 
Allowable stresses 
41 
11.8 
Independent analysis 
41 
12 
LIFT POINT DESIGN 
42 
12.1 
Introduction 
42 
12.2 
General design requirements 
42 
12.3 
Lateral lift point load 
42 
12.4 
Sling ovalisation 
42 
12.5 
Padeyes 
43 
12.6 
Cast Padears and welded trunnions 
43 
12.7 
Inspection of lift points 
43 
13 
FABRICATION YARD LIFTS 
45 
13.1 
Introduction 
45 
13.2 
Weight and CoG 
45 
13.3 
Additional loads 
45 
13.4 
Dynamic loads 
45 
13.5 
Load cases 
46 
13.6 
Lifting equipment 
46 
13.7 
Fabrication yard cranes 
46 
13.8 
Operational and practical considerations for onshore lifts 
46 
14 
FABRICATION OF RIGGING AND LIFTING EQUIPMENT 
48 
14.1 
Introduction 
48 
14.2 
Materials and construction of steel slings and grommets 
48 
14.3 
Materials and construction of fibre slings and grommets 
48 
14.4 
Materials and construction of shackles 
49 
14.5 
Materials and construction of lifting tools 
49 
14.6 
Materials and construction of spreader bars and spreader frames 
50 
14.7 
Materials and construction of other lifting equipment 
51 
15 
CERTIFICATION AND INSPECTION OF RIGGING AND LIFTING EQUIPMENT 
52 
15.1 
Introduction 
52 
15.2 
Certification, inspection and revalidation of slings and grommets 
52 
15.3 
Certification and Inspection of shackles 
54 
15.4 
Certification and Inspection of lifting tools 
55 
15.5 
Certification and Inspection of spreader bars and spreader frames 
55 
15.6 
Certification and Inspection of other lifting equipment 
55 
16 
CLEARANCES 
57 
16.1 
Introduction 
57 
16.2 
Clearances around lifted object (floating crane) 
57 
16.3 
Clearances around lifted object (jacked-up crane) 
57 
16.4 
Clearances around crane vessel 
58 
16.5 
Clearances around mooring lines and anchors 
58 
16.6 
Clearances for fabrication yard lifts 
58 
17 
BUMPERS AND GUIDES 
59 
17.1 
Introduction 
59 
17.2 
Module movement 
59 


GUIDELINES
 
FOR
 
MARINE
 
LIFTING
 
&
 
LOWERING
 
OPERATIONS 
0027/ND Rev 11 
 
Page 5 of 84 
17.3 
Position of bumpers and guides 
59 
17.4 
Bumper and guide forces 
60 
17.5 
Design considerations 
60 
18 
OPERATIONS AND PRACTICAL CONSIDERATIONS 
62 
18.1 
Organisation, planning and documentation 
62 
18.2 
Safety 
64 
18.3 
Weather-restricted operations and weather forecasts 
64 
18.4 
Environmental design criteria 
64 
18.5 
Survey and positioning 
64 
18.6 
Vessel motions and operational details 
64 
18.7 
Safe access 
65 
18.8 
Loose equipment 
65 
18.9 
Seafastening removal and lifting operations 
65 
18.10 Slings & shackles 
66 
18.11 Spreader bars and spreader frames 
68 
18.12 Load and motion limiting systems 
68 
19 
INSTALLATION OF SUBSEA EQUIPMENT 
69 
19.1 
Scope 
69 
19.2 
Design principles 
69 
19.3 
Subsea lifting requirements (additional to those in air) 
70 
19.4 
Deployment system 
71 
19.5 
Positioning and landing 
71 
19.6 
ROV systems 
72 
19.7 
Testing 
72 
19.8 
Suction piles & foundations 
73 
19.9 
Driven anchor piles 
73 
19.10 Jumpers and tie-in spools 
74 
19.11 Rigid pipe riser installation 
74 
19.12 Subsea storage tanks 
75 
REFERENCES 
77 
APPENDIX A - INFORMATION REQUIRED FOR APPROVAL 
78 
APPENDIX B - GUIDELINES FOR DERIVATION OF DESIGN LOADS 
81 
 
TABLES 
Table 

4-1 
Typically Required Surveys 
20 
Table 

5-1 
Dynamic Amplification Factors (DAF) in Air 
24 
Table 

7-1 
Bending Factors 
33 
Table 

11-1 
Consequence Factors 

c
 
40 
Table 

17-1 
Default Bumper & Guide Forces (Offshore) 
60 
FIGURES 
Figure 

5-1 
Lift Calculation Flowchart 
22 
Figure 

6-1 
Resolving Sling Loading 
29 
Figure 

12-1 
Indicative shaping of padear bearing surface 
43 
Figure 

B-1 
Derivation of Tilt Factor for CoG Below Lift Points 
82 
Figure B-2 
Derivation of Lift Point Loads 
83 
 


GUIDELINES
 
FOR
 
MARINE
 
LIFTING
 
&
 
LOWERING
 
OPERATIONS 
0027/ND Rev 11 
 
Page 6 of 84 

SUMMARY 
1.1 
These guidelines have been developed for the design and approval of marine lifting operations, 
including subsea installations (but excluding pipelines and flowlines). 
1.2 
This document supersedes the previous revision, document No. 0027/ND Rev 10 dated 23 June 2013.
The changes are described in Section 2.14. 
1.3 
These guidelines cover lifting operations by floating crane vessels, including crane barges, crane 
ships, semi-submersible crane vessels and jack-up crane vessels. They also include subsea 
installations using a crane, winch or derrick. They may also be applied to lifting operations by land-
based cranes for the purpose of load-out. They are intended to lead to an approval by GL Noble 
Denton, which may be sought where an operation is the subject of an insurance warranty, or where an 
independent third party review is required. 
1.4 
A description of the approval process is given for those projects which are the subject of an insurance 
warranty. 
1.5 
The report includes guidelines for the load and safety factors to be applied at the design stage. 
1.6 
Comments on the practical aspects of the management of the operation are also offered. 



Yüklə 1,31 Mb.

Dostları ilə paylaş:
1   2   3   4   5   6   7   8   9   ...   97




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©www.azkurs.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin